Wednesday, November 28, 2012
Framing Stage completed on 16th Nov 12
Saturday, November 10, 2012
Week 2 (slab done)
Hi all sorry for disapearing from blog for a while. Our block has finally been slabbed.
Have a look at the pics i have taken this afternoon. The lower lever is where our garage will be. And there will be steps into the house.
One thing that we re not happy about is the fence. There is a panel which has been dented and our neighbour has complaint as well .
Hope they will be responsible for the broken panel.
Thursday, October 25, 2012
Finally Site start today
Tuesday, September 18, 2012
Further updates
Next we only need to hear from the builder when council approve the plan. Should approval come through this month, they would probably start the excavation in October. Meaning 98 days from October 2012 our house will be ready. Finger crossed ++++.
We have visited the land last Sunday (16.09) , to ensure the pegs are still available. Since if builder can't find these pegs when they are onsite,it's gonna cost us almost $900, just to get surveyor to re-measure the land again.
We have found 3pegs so far , cant find the other one....
. According to Stockland's sales person normally builder only need 3 pegs. Hopefully the three pegs will be sufficient.Here are picture of the land n yes we have got a fence on the left side since the neighbor has settled in recently.
And the color bond fence which we share with our neighbor cost us almost $900 just for the left side.Sunday, August 19, 2012
Color selection ( week 2)
Here is the picture of color selection we have selected.
Color we choose for internal & external of the house. And the facade of the hose **except the color will be different. |
EIGHTHOMES offer us 4 different packages which colors have been pre-selected by their interior designer. For customer like me n my husband, we don't mind this method , since we believe it is more convenient.
So basically we are waiting for them to contact us to sign the tender / contract after they have received approval fron the developer.
And then they could start the build.
Really looking forward...
Cheers
Thursday, August 16, 2012
Glass or tiles Splash back for your kitchen?
Tiles Splash back for Kitchen |
Glass Splash back for Kitchen |
Erni
Wednesday, August 15, 2012
The floor plan We choose
Bought the Land
My husband and I had bought a land in the North Area, far far away from where I live now that I called it as jungle. :)We bought the land since officially in March 2012, but we reserved the land since Oct 2011. Here are pictures taken last year.
We decided to build with a builder called Eight Homes (www.8homes.com.au). We found them when we visited display houses in Tarneit - VIC. Until we saw their welcome pack promotion which include the driveway & landscaping which is last until last Sunday 11th Aug 2012. We then visited their display house in Cranbourne West/ North, not sure exactly since I am not good with directions. And since we like the design and the quality of their display we decided to pay the deposit on the same visit.